COPEData is free. 100 reports every month for every user. No credit card, no trial clock.

COPEData
All guides
ConstructionISO

ISO construction classes 1–6, explained with examples

Frame to fire resistive: ISO's six construction classes defined, how to spot each, the 66⅔% mixed-construction rule, and how IBC types map to them.

October 30, 2026 · 14 min read · COPEData

A listing that calls a building “brick” hasn't told you its ISO construction class. The brick may be veneer over wood studs, or it may form load-bearing walls beneath a wood roof. Those details affect the class recorded on a statement of values, with consequences for fire rating and catastrophe modeling.

ISO classification depends on the exterior walls, floors and roof, including their fire resistance. The six classes below provide a starting point; mixed materials and additions require a closer look. For context on the other underwriting fields, see what COPE data is.

The six classes at a glance

ISO sorts buildings into six classes, from most combustible to least. The definitions below follow ISO's published Guide for Determination of Needed Fire Flow (Edition 06-2014, Chapter 2). The same six classes and names are used in ISO's Commercial Lines Manual, which is a subscriber document.

ClassNameExterior wallsFloors and roofFire-resistance threshold
1FrameCombustible, or non-combustible walls with combustible floors and roofCombustibleNone
2Joisted masonryMasonry, or fire-resistive rated at least 1 hourCombustibleWalls only: masonry or ≥1 hr
3Non-combustibleNon-combustible or slow-burningNon-combustible or slow-burning, on non-combustible supportsNone
4Masonry non-combustibleMasonry at least 4 in. thick, or fire-resistive ≥1 hrNon-combustible or slow-burningWalls only: masonry or ≥1 hr
5Modified fire resistiveMasonry or fire-resistiveFire-resistive1 hour to under 2 hours
6Fire resistiveMasonry or fire-resistiveFire-resistive2 hours or more
Six classes, three building parts
CombustibleNon-combustible, unratedMasonry (≥4 in.) or ≥1-hr ratedFire resistive, 1 to <2 hrFire resistive, ≥2 hrSlab on grade (ignored)
1Frame
Walls
Wood or other combustible framing, including brick veneer or stucco over studs
Floors
Wood joists or trusses
Roof
Wood trusses, wood deck
Garden apartments, wood-framed offices and retail, pole barns
2Joisted masonry
Walls
Brick, block, poured or tilt-up concrete
Floors
Wood joists or heavy timber
Roof
Wood joists, glulam, panelized wood deck
Main-street brick buildings, CMU strip centers, tilt-ups with wood roofs
3Non-combustible
Walls
Metal panels on steel girts
Floors
Steel framing, if any
Roof
Metal deck on steel purlins
Pre-engineered metal buildings, steel-stud shells
4Masonry non-combustible
Walls
Block, brick or tilt-up concrete
Floors
Concrete on metal deck, steel joists
Roof
Metal deck on steel bar joists
Modern warehouses, big-box retail, block-and-bar-joist buildings
5Modified fire resistive
Walls
Masonry or rated assemblies, 1 to <2 hr
Floors
Protected steel or concrete, 1 to <2 hr
Roof
Protected deck and supports, 1 to <2 hr
Mid-rise offices and hotels with 1-hr protected steel
6Fire resistive
Walls
Reinforced concrete or ≥2-hr assemblies
Floors
Concrete slabs ≥4 in. or ≥2-hr assemblies
Roof
Concrete or ≥2-hr assembly
High-rise offices, hospitals, concrete parking decks
Each panel is a schematic two-story section. Color shows how ISO treats the material, not what it looks like. The slab on grade is drawn neutral because ISO disregards the lowest floor and below-grade basement walls when classifying.
Source: Definitions from ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2 §1–2. Diagram by COPEData.

Classify the walls separately from the floors and roof, then combine the results. The fire-resistance thresholds apply throughout the structure for Classes 5 and 6, but only to the walls for Classes 2 and 4. A block building with bare steel bar joists and a metal deck can therefore be Class 4 despite the roof's vulnerability to fire.

What "combustible" means to ISO

Several terms have specific meanings in ISO's fire flow guide (Ch. 2 §1):

  • Masonry veneer is combustible. "Combustible wall materials with an exterior surface of brick, stone, or other masonry materials (commonly known as 'masonry veneer')" are listed as combustible. A brick-faced apartment building with wood studs behind the brick is Frame.
  • Wood-iron clad is combustible. Metal siding or roofing on a wood skeleton (a pole barn, for example) is combustible construction.
  • A metal roof can be combustible. Metal floors or roofs with combustible insulation or ceiling material attached to the underside, or within 18 inches of the supports, count as combustible. So do composite panels with a combustible or foam-plastic core, unless the foam qualifies as slow-burning behind an acceptable thermal barrier.
  • Rated wood is still wood. "Combustible assemblies which are listed as having not less than a one-hour rating" remain combustible. A one-hour wood-stud wall with Type X gypsum is a rated combustible wall, not a fire-resistive one. ISO reserves "fire-resistive" for non-combustible materials or assemblies rated at least one hour.
  • Masonry means at least 4 inches. Adobe, brick, concrete, block, stone, tile and similar materials qualify as masonry at a minimum thickness of 4 inches. Masonry walls thinner than that, standing on their own, are non-combustible but not masonry.
  • Non-combustible includes unrated protection. Steel with fireproofing rated under one hour is just "non-combustible" for ISO purposes. Furring strips nailed to non-combustible supports don't change a wall's class.

Class by class

Class 1: Frame

Definition. Exterior walls, floors and roof of combustible construction, or non-combustible/slow-burning walls carrying combustible floors and roof.

Typical buildings. Garden-style and mid-rise wood apartments, wood-framed strip retail, small offices, houses converted to offices, pole barns, and most podium buildings (more on those below).

How to spot it. Look for a sloped roof on wood trusses, siding, vinyl or fiber-cement cladding, stucco on a building under four or five stories, and walls that sound hollow when tapped. Brick that ends at the window sill or has weep holes and a visible air gap is veneer. Permit records that mention "framing," "shear wall," or "trusses" settle it; the building permit history guide covers how to read them.

Common errors. Coding brick-veneer apartments as joisted masonry; coding a metal-sided building as Class 3 when the girts and purlins are wood; treating stucco as masonry.

Class 2: Joisted masonry

Definition. Exterior walls of masonry (at least 4 inches) or of fire-resistive construction rated at least one hour, with combustible floors and roof.

Typical buildings. Pre-war brick main-street buildings with wood joists, concrete-block strip centers with wood trusses, and tilt-up warehouses with panelized wood roofs (glulam beams, wood purlins, plywood or OSB deck). Heavy-timber mill buildings fall here too, because ISO treats timber as combustible no matter how thick it is.

How to spot it. Masonry or concrete walls you can see from both sides at doors and window returns, plus a wood ceiling structure when you look up inside. In a warehouse, a wood roof deck shows as plywood panels between purlins.

Common errors. Assuming every tilt-up is Class 4. The walls qualify as masonry, but the roof structure decides between 2 and 4, and panelized wood roofs are common on tilt-ups, especially in the West.

Class 3: Non-combustible

Definition. Exterior walls, floors and roof of non-combustible or slow-burning materials on non-combustible or slow-burning supports. No hourly rating is required.

Typical buildings. Pre-engineered metal buildings (steel frame, metal wall panels, metal roof), and steel-stud buildings with non-combustible sheathing.

How to spot it. Corrugated or ribbed metal walls with steel columns and girts visible inside, a metal roof on steel purlins, and no masonry wainscot taller than a few feet.

Common errors. Treating every "metal building" as Class 3. Foam-core insulated metal panels that don't meet the slow-burning criteria, foam insulation stuck to the underside of the deck, or wood girts and purlins all make the assembly combustible, which can drop it to Class 1.

Class 4: Masonry non-combustible

Definition. Exterior walls of masonry at least 4 inches thick or fire-resistive rated at least one hour, with non-combustible or slow-burning floors and roof. The roof deck stays non-combustible even with combustible roof insulation, felt or tar on top.

Typical buildings. Modern distribution warehouses (tilt-up or block walls, steel joists, metal deck), big-box retail, and many one-story schools and medical office buildings.

How to spot it. Masonry or concrete walls plus open-web steel bar joists and a fluted metal deck overhead. No spray fireproofing on the steel.

Common errors. Calling these "fire resistive" because they are "concrete buildings." Without rated floors and roof, concrete walls alone stop at Class 4.

Class 5: Modified fire resistive

Definition. Exterior walls, floors and roof of fire-resistive materials rated at least one hour but under two hours, or of masonry that is at least 4 inches thick but short of Class 6 thickness requirements.

Typical buildings. Mid-rise offices, hotels and medical buildings with one-hour protected steel; some older concrete-frame buildings with thin slabs.

How to spot it. Spray-applied fireproofing or gypsum-encased steel columns and beams, concrete-on-deck floors, and design documents listing one-hour (or 1½-hour) assemblies. This class rarely gets identified from the street; it usually comes from plans or a survey.

Class 6: Fire resistive

Definition. Exterior walls or structural frame of solid masonry or reinforced concrete at least 4 inches thick (or rated assemblies of at least two hours); floors and roof of monolithic reinforced concrete slabs at least 4 inches, concrete joist systems meeting ISO's spacing and slab rules, or two-hour assemblies; and load-bearing protected steel rated at least two hours.

Typical buildings. High-rise office towers, cast-in-place concrete residential towers, hospitals, and concrete parking structures.

How to spot it. Cast-in-place concrete columns and flat slabs, or heavily fireproofed steel in a high-rise. The building height alone is often a clue: tall buildings are usually built to Type I under the building code (see the IBC section below).

Which class is it?

When the materials are known, the class follows from five questions asked in order. Each question applies to the building as a whole; if no single answer covers at least two-thirds of the relevant area, go to the mixed construction rules in the next section.

A five-question decision ladder
  1. 1
    Is more than one-third of the exterior wall area combustible?
    Wood or steel studs sheathed in wood, brick or stone veneer over studs, metal siding on a wood frame, foam-core panels, rated wood assemblies.
    YesClass 1 · Frame
    No↓ next question
  2. 2
    Are the floors and roof combustible?
    Wood joists or trusses, glulam, heavy timber, wood deck; also a metal deck with combustible insulation stuck to its underside.
    YesClass 2 if walls are masonry or ≥1-hr rated; otherwise Class 1
    No↓ next question
  3. 3
    Are the exterior walls masonry (≥4 in.) or rated ≥1 hour?
    Block, brick, tilt-up or poured concrete. Metal panels on girts are non-combustible but not masonry.
    Yes↓ next question
    NoClass 3 · Non-combustible
  4. 4
    Are the floors and roof also rated ≥1 hour?
    Spray-fireproofed or encased steel, concrete slabs. Bare bar joists and metal deck are unrated.
    Yes↓ next question
    NoClass 4 · Masonry non-combustible
  5. 5
    Do walls, floors and roof all reach ≥2 hours?
    Reinforced concrete slabs ≥4 in., concrete or 2-hr protected frame, solid masonry ≥4 in.
    YesClass 6 · Fire resistive
    NoClass 5 · Modified fire resistive
Answer from the top. Ignore below-grade basement walls and the lowest floor. A metal deck with combustible insulation attached underneath counts as a combustible roof.
Source: Derived from ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2 §1–3. Diagram by COPEData.

Mixed construction and the 66⅔% rule

Real buildings mix materials: a concrete podium under wood floors, block walls on three sides and an EIFS-clad office front, a steel addition on a wood-roofed warehouse. ISO's mixed construction rule (fire flow guide, Ch. 2 §3) works from the most protective class down:

  1. Fire resistive if at least 66⅔% of the total wall area and at least 66⅔% of the total floor-and-roof area meet Class 6.
  2. Modified fire resistive if both shares meet Class 5, or Classes 5 and 6 together reach 66⅔% without either one doing it alone.
  3. Masonry non-combustible on the same test for Class 4, or Classes 4–6 combined.
  4. Non-combustible on the same test for Class 3, or Classes 3–6 combined.
  5. Joisted masonry if at least 66⅔% of the wall area is Class 2 construction, or Classes 2–6 combined reach 66⅔% of both walls and floor-and-roof area.
  6. Frame for anything left, and for any building with more than 33⅓% of its total wall area combustible, regardless of the rest of the building.

The combustible-wall threshold matters even in buildings with substantial concrete construction. Above one-third combustible wall area, the rule assigns Frame. Basement walls and the lowest floor are disregarded throughout.

Try it: a tilt-up office/warehouse with an EIFS front
Combustible 25%Tilt-up concrete 75%
Vertical rule marks 33⅓% of wall area.
Combustible 20%Metal deck on steel joists 80%
Vertical rule marks the point where non-combustible area drops below 66⅔%.
Result
Class 4 · Masonry non-combustible
At least 66⅔% of the wall area is masonry and at least 66⅔% of the floor-plus-roof area is non-combustible (rule 3c).
Illustrative example, simplified. The non-combustible share of the walls is tilt-up concrete; the non-combustible floor and roof is metal deck on steel joists. Move either slider across its rule to see the class change.
Source: Rules from ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2 §3(c), (e), (f). Widget by COPEData.

The podium problem

Five-over-one and similar podium buildings are the most common place this rule changes a submission. Picture a hypothetical building with one story of cast-in-place concrete for parking and retail, and four stories of wood-framed apartments above. Ignoring the lowest floor, the floor-and-roof area is four wood floor plates plus a wood roof over a single concrete podium deck. The wall area is about four-fifths wood studs. With more than 33⅓% of the walls combustible, the building is Class 1 under ISO's rule, even though the ground floor would be Class 6 on its own. Some carriers rate the podium and the frame portion separately when a rated horizontal separation exists; that is a carrier-specific practice, so check the guidelines you're writing under.

ISO classes vs. IBC construction types

Architects, building departments and many listings describe buildings using the International Building Code's construction types (I-A through V-B). The IBC types are defined by Table 601, which sets minimum fire-resistance ratings in hours for each building element. The values below are from the 2015 IBC (ICC, Chapter 6); they were carried forward in later editions, which also added three mass timber types.

IBC typeStructural frameExterior bearing wallsFloorsRoofUsual ISO class
I-A3 hr3 hr2 hr1½ hr6
I-B2 hr2 hr2 hr1 hr6 (sometimes 5)
II-A1 hr1 hr1 hr1 hr5 (often coded 4)
II-B00003 with metal walls, 4 with masonry walls
III-A1 hr2 hr1 hr1 hr2 with masonry walls; 1 with treated-wood walls
III-B02 hr002 with masonry walls; 1 with treated-wood walls
IV-HTHeavy timber2 hrHeavy timberHeavy timber2
V-A1 hr1 hr1 hr1 hr1
V-B00001
Where each IBC type usually lands
Usual landing spotPossible, depending on walls and ratings
ISO class ↓ / IBC type →I-AI-BII-AII-BIII-AIII-BIV-HTV-AV-B
6 Fire resistive
5 Modified FR
4 Masonry NC
3 Non-combustible
2 Joisted masonry
1 Frame
Approximate. The IBC classifies by hourly ratings of structural elements; ISO classifies by material combustibility and wall/floor/roof ratings. The two systems answer different questions, so a mapping is a starting point for review, not a substitute for it.
Source: IBC 2015 Table 601 (ICC); ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2. Mapping by COPEData.

The rows that need care:

  • I-B. Floors and walls are rated two hours, the roof one hour. Under the mixed construction rule, a building of three or more stories usually has enough two-hour floor area to clear 66⅔% of the floor-and-roof total, which lands it in Class 6. Low-rise I-B buildings can fall to Class 5.
  • II-A. Every element is rated one hour and non-combustible, which matches ISO's Class 5 definition. In practice many submissions code these Class 4, often because the roof protection isn't documented. Ask for the code analysis on the drawings before giving Class 5.
  • II-B. No hourly ratings at all, so the wall material decides: metal panels give Class 3; block or tilt-up walls give Class 4.
  • III-A and III-B. The IBC allows fire-retardant-treated wood framing in Type III exterior walls. To ISO, a rated wood assembly is still combustible, so a Type III building with treated-wood exterior walls is Frame. Type III with true masonry walls is joisted masonry.
  • Mass timber (IV-A, IV-B, IV-C). The 2021 IBC added these types for tall mass timber buildings, up to 18 stories for IV-A (STRUCTURE magazine). ISO's six-class definitions treat timber as combustible, so a literal reading puts them in Class 1 or 2 depending on the exterior walls. Carriers differ on how much credit they give for encapsulation and sprinklers.

Why construction class moves the rate

Construction class is a proxy for how much of the building is fuel and how long the structure stays up. In a Frame building the structure itself burns; in a fire-resistive building the fire is largely limited to contents and finishes on the floor of origin, and the frame is usually repairable. That difference shows up directly in ISO's own math. The fire flow guide calculates a construction factor C = 18 × F × √A, where A is the effective area and F is a coefficient set by construction class. ISO rounds C to the nearest 250 gpm, with a 500 gpm floor and caps of 8,000 gpm for Classes 1–2 and 6,000 gpm for Classes 3–6 (and for any one-story building).

1.5
F for Frame
Class 1
1.0
F for joisted masonry
Class 2
0.8
F for non-combustible
Classes 3 and 4
0.6
F for fire resistive
Classes 5 and 6
Source: ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2.
Needed fire flow construction factor by class
Same footprint, same occupancy: the Frame building needs 2.5× the fire flow of the fire-resistive one.
1 Frame3,750 gpm
2 Joisted masonry2,500 gpm
3 Non-combustible2,000 gpm
4 Masonry NC2,000 gpm
5 Modified FR1,500 gpm
6 Fire resistive1,500 gpm
View data
CategoryValue (gpm)Note
1 Frame3,750F = 1.5
2 Joisted masonry2,500F = 1
3 Non-combustible2,000F = 0.8
4 Masonry NC2,000F = 0.8
5 Modified FR1,500F = 0.6
6 Fire resistive1,500F = 0.6
Drag to change the effective area. Bars show ISO's construction factor C in gallons per minute for the same building under each class. It excludes occupancy, exposure and communication factors, which ISO applies afterward. The one-story cap of 6,000 gpm is not applied here.
Source: Formula, coefficients, rounding and caps from ISO, Guide for Determination of Needed Fire Flow, Ed. 06-2014, Ch. 2 §5. Calculator by COPEData.

At a 20,000 sq ft effective area, a Frame building needs 3,750 gpm and a fire-resistive one 1,500 gpm: 2.5 times the water for the same footprint. Fire flow isn't premium, but the same logic runs through rating. Commercial property rating plans, ISO's included, vary fire loss costs by construction class, and catastrophe models use the class (or a finer version of it) as a primary input. A one-class error on a large schedule can move the modeled loss more than most other single fields.

What new construction is actually made of

Wood framing accounts for most new U.S. residential construction. The Census data below helps explain why an exterior finish alone is a poor basis for assigning a masonry class.

Wood is still the default framing material
Single-family housesMultifamily bldgs
Share of new construction that is wood-framed
Single-family houses, Multifamily bldgs0%50%100%200920122015201820212024Single-family housesMultifamily bldgs
View data
Single-family housesMultifamily bldgs
200995%86%
201095%84%
201195%85%
201294%87%
201394%87%
201493%86%
201593%87%
201691%84%
201792%84%
201893%84%
201990%82%
202091%85%
202192%87%
202294%88%
202393%89%
202494%86%
202594%83%
Share of new single-family houses and new multifamily buildings completed each year with wood framing. The multifamily remainder is mostly steel, concrete and insulated concrete forms.
Source: U.S. Census Bureau, Survey of Construction, Characteristics of New Housing: framing_cust.xls (SFTotalFrame) and mfb_framing_cust.xls (MFBFrameAll), U.S. rows, 2009–2025. Retrieved 2026-10-30.

Between 2009 and 2025, 90% to 95% of new single-family houses and 82% to 89% of new multifamily buildings were wood-framed. Brick doesn't change that. In 2025, 164,000 new single-family houses had brick as the primary exterior wall material, but only 53,000 houses of any cladding had concrete framing and 5,000 had steel framing. Even if every concrete- and steel-framed house were brick-clad, at least 106,000 of the brick houses, or about 65%, had to be brick veneer over wood. In the South, where most brick is used, the same arithmetic gives at least 98,000 of 151,000.

Brick on the outside, wood on the inside
Brick primary exterior164 thousand houses
Concrete framing (incl. ICF)53 thousand houses
Steel framing5 thousand houses
View data
CategoryValue (thousand houses)
Brick primary exterior164
Concrete framing (incl. ICF)53
Steel framing5
New single-family houses completed in 2025, in thousands. Brick-clad houses outnumber all concrete- and steel-framed houses combined by about three to one, so most brick in new construction is veneer: ISO Class 1.
Source: U.S. Census Bureau, Characteristics of New Housing: exwallmat_cust.xls (SFTotalExWallMat) and framing_cust.xls (SFTotalFrame), U.S., 2025. Retrieved 2026-10-30.

Translating assessor codes and listing descriptions

At quote stage, the available records may be limited to an assessor entry, a broker's SOV and a sale or lease listing. Read their construction descriptions carefully: they may use a different classification system.

Assessor construction class

Many assessors classify buildings with a cost-manual system built around A, B, C, D and S construction types. California's State Board of Equalization publishes a representative set in Assessors' Handbook Section 531.10A (January 2025):

Assessor typeWhat the handbook describesLikely ISO classWatch for
AStructural steel frame fireproofed with concrete or spray, concrete floors and roof6 or 5Rating of the fireproofing
BReinforced concrete columns and beams, concrete floors and roof6 or 5Slab thickness, older thin slabs
CMasonry exterior walls; floors of wood or poured concrete; wood roof structure2 (4 if the roof is steel)Roof framing decides 2 vs. 4
DWood frame; skin may be wood, stucco, masonry veneer or sheet metal1Veneer that looks like masonry
SSpecialized buildings that fit none of the aboveVariesIn many other jurisdictions "S" means pre-engineered steel (often Class 3)

Check whether a number refers to quality class before copying it. Assessor codes such as “D6A” or “C5” can combine a construction type with a quality grade and a shape letter. In “D6A,” D identifies the construction type and 6 the quality grade. These codes support cost estimating and do not map directly to ISO classes. They may also predate a remodel or addition.

Listing and SOV language

PhraseWhat it usually meansISO class it supports
"Brick," "all brick," "brick exterior"Brick veneer on most newer buildings; possibly solid multi-wythe masonry in older ones1 unless solid masonry is confirmed
"Concrete block," "CMU," "masonry"Masonry walls2 or 4, depending on the roof
"Tilt-up," "tilt-wall"Concrete wall panels2 with wood roof, 4 with steel joists and metal deck
"Steel building," "metal building," "PEMB"Pre-engineered metal3, or 1 if wood girts or foam panels
"Steel frame" on an office or hotelCould be protected or bare steel3 to 6; ask about fireproofing
"Concrete construction," "post-tensioned"Concrete frame and slabs5 or 6
"Five-over-one," "podium"Wood over concrete1 under the 66⅔% rule

A short field checklist

Before you accept a construction class on a schedule, confirm five things:

  1. What the exterior walls are made of behind the cladding. Veneer, stucco and EIFS describe the skin, not the wall.
  2. What holds up the roof. Wood trusses or a panelized wood deck make it 1 or 2; steel joists and metal deck make it 3 or 4.
  3. Whether anything is rated, and for how long. Classes 5 and 6 need documentation: plans, a code analysis, or a survey.
  4. The share of each construction type by area. If more than a third of the wall area is combustible, the building is Frame.
  5. What changed since it was built. Additions, re-roofs and façade replacements alter the class; permit records are the fastest way to find them (see building permit history).

The class you settle on then feeds the construction column of the SOV, alongside year built, stories and area. The statement of values guide covers how that column is used downstream.

Get the COPE data for any property, free
Type an address and COPEData compiles construction, occupancy, protection and exposure data in about a minute, with every value linked to its source. 100 free reports every month.
Run a free report
Keep reading